Building permit fees for a commercial project total $12,500. If the jurisdiction charges a 3.5% convenience fee for online payments and a 2.8% fee for credit card processing, what is the total amount due when paying online with a credit card?
Correct Answer
B) $13,294.38
First add convenience fee: $12,500 × 1.035 = $12,937.50. Then add credit card fee: $12,937.50 × 1.028 = $13,294.38. Both fees compound on the total amount.
Why This Is the Correct Answer
Option C is correct because both fees must be calculated sequentially (compounding). The convenience fee is applied first to the base permit fee ($12,500 × 1.035 = $12,937.50), then the credit card processing fee is applied to the new total including the convenience fee ($12,937.50 × 1.028 = $13,294.38). This reflects how payment processors typically structure their fee calculations in real-world scenarios.
Why the Other Options Are Wrong
Option A: $13,287.50
This answer likely adds both percentages together (3.5% + 2.8% = 6.3%) and applies them simultaneously to the base amount, which is incorrect since fees compound sequentially.
Option C: $13,350.00
This answer appears to use rounded numbers or incorrect percentages, resulting in an amount that doesn't match the proper sequential calculation of both fees.
Memory Technique
Think 'COMPOUND FEES' - like compound interest, each fee builds on the previous total. Use the acronym 'FIRST THEN' - apply the FIRST fee, THEN apply the second fee to the new amount.
Reference Hint
Florida Building Code Chapter 1 - Administration and Enforcement, specifically sections on permit fees and administrative costs
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
During construction, a mechanical contractor relocates ductwork 3 feet from its original design location to avoid a structural beam conflict. Who is typically responsible for updating the as-built drawings?
Next Question
In a Guaranteed Maximum Price (GMP) contract, the contractor's fee is $85,000 and the GMP is set at $1,200,000. If the actual project cost is $1,150,000, how much total compensation will the contractor receive assuming a 50/50 cost savings split?
