EstatePass
Contract AdminContractseasy40% of exam part

In a unit price contract, excavation is priced at $12.50 per cubic yard. If the actual excavation required is 2,840 cubic yards, what is the total cost for excavation?

Correct Answer

A) $35,500

Unit price contracts multiply the actual quantity by the agreed unit price. Total cost = 2,840 cubic yards × $12.50 per cubic yard = $35,500.

Answer Options
A
$35,500
B
$35,000
C
$36,200
D
$34,800

Why This Is the Correct Answer

In a unit price contract, the total cost is calculated by multiplying the actual quantity of work performed by the predetermined unit price. This is a straightforward multiplication problem: 2,840 cubic yards × $12.50 per cubic yard = $35,500. Unit price contracts are designed to accommodate variations in actual quantities while maintaining a fixed rate per unit of work.

Why the Other Options Are Wrong

Option B: $35,000

This answer of $35,000 appears to be the result of rounding or estimation error, possibly from calculating 2,800 × $12.50 instead of using the actual quantity of 2,840 cubic yards.

Option C: $36,200

This answer of $36,200 is too high and likely results from a calculation error, possibly adding an extra amount or using an incorrect unit price in the multiplication.

Option D: $34,800

This answer of $34,800 is too low and appears to result from using an incorrect quantity or unit price, possibly calculating with 2,784 cubic yards instead of 2,840.

Memory Technique

Remember 'UPC' - Unit Price Contract = Unit price × Quantity = Cost. Always multiply the ACTUAL quantity by the AGREED unit price.

Reference Hint

Look up 'Unit Price Contracts' or 'Contract Types' in construction management or estimating chapters of your reference materials

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing