In a lump sum contract, what is the primary risk assumed by the general contractor?
Correct Answer
A) Material price fluctuations and cost overruns
In a lump sum contract, the contractor agrees to complete the work for a fixed price, assuming the risk of cost overruns, material price increases, and other unforeseen expenses. The contractor must absorb these costs unless covered by change orders.
Why This Is the Correct Answer
In a lump sum contract, the contractor agrees to complete the project for a fixed price regardless of actual costs incurred. This means the contractor bears the financial risk if materials become more expensive, labor costs increase, or unexpected expenses arise during construction. The contractor cannot pass these additional costs to the owner unless there are approved change orders for scope changes. This risk-reward structure is the fundamental characteristic that distinguishes lump sum contracts from cost-plus contracts.
Why the Other Options Are Wrong
Option B: Owner's ability to pay
While the owner's ability to pay is always a concern, this is not the primary risk specific to lump sum contracts. Payment risk exists in all contract types and is typically addressed through payment bonds, lien rights, and credit checks during the bidding process.
Option C: Weather delays only
Weather delays are just one type of risk among many that contractors face in lump sum contracts. The primary risk encompasses all cost overruns, including but not limited to weather-related delays, material price increases, labor cost fluctuations, and unforeseen conditions.
Option D: Subcontractor performance only
Subcontractor performance is only one component of the overall cost risk in lump sum contracts. While poor subcontractor performance can lead to cost overruns, the primary risk includes all potential cost increases including materials, labor, equipment, and other project expenses.
Memory Technique
Think 'LUMP SUM LUMPS ALL RISKS ON CONTRACTOR' - the fixed price means the contractor absorbs all cost increases that aren't covered by change orders.
Reference Hint
Florida Building Construction Standards - Chapter on Contract Types and Risk Allocation, or Construction Law section covering contract delivery methods
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A concrete pour fails the 28-day compressive strength test. The test shows 2,800 psi when the specification requires 3,000 psi. What should be the contractor's first action?
Next Question
What is the standard inspection sequence for a typical single-family residential construction project?