EstatePass
Contract AdminContractsmedium40% of exam part

According to Florida lien law, how long does a contractor have to record a Claim of Lien after the last day of providing labor or materials?

Correct Answer

B) 90 days

Under Florida Statute Chapter 713, a contractor must record a Claim of Lien within 90 days after the last day they provided labor, services, or materials to the improvement.

Answer Options
A
60 days
B
90 days
C
120 days
D
180 days

Why This Is the Correct Answer

Florida Statute Chapter 713 specifically establishes that contractors must record their Claim of Lien within 90 days after the last day they provided labor, services, or materials to the improvement. This 90-day timeframe is a strict statutory requirement that cannot be extended or waived. Missing this deadline results in the complete loss of lien rights, making it one of the most critical deadlines in Florida construction law. The 90-day period begins running from the contractor's last day of work, not from project completion or final payment requests.

Why the Other Options Are Wrong

Option A: 60 days

60 days is too short and not the timeframe established by Florida Statute Chapter 713 for recording a Claim of Lien

Option C: 120 days

120 days exceeds the statutory timeframe and would result in loss of lien rights under Florida law

Option D: 180 days

180 days is far beyond the statutory deadline and would result in complete loss of lien rights

Memory Technique

Think '90 days to save your pay' - the 90-day deadline is your last chance to protect your right to payment through a lien

Reference Hint

Florida Statute Chapter 713 - Construction Liens, specifically Section 713.08

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing