EstatePass
Contract AdminProcedureseasy13% of exam part

As-built drawings are typically required to be submitted:

Correct Answer

C) Before final payment and project closeout

As-built drawings are standard deliverables required before final payment and project closeout, documenting the actual constructed conditions for the owner's permanent records.

Answer Options
A
Weekly during construction progress
B
At the completion of each major construction phase
C
Before final payment and project closeout
D
Only when specifically requested by the owner

Why This Is the Correct Answer

As-built drawings are contractually required deliverables that document the final constructed conditions, showing any deviations from the original plans. They serve as permanent record drawings for the owner's facility management and future renovations. These drawings are essential for project closeout and are typically a prerequisite for final payment release. The timing before final payment ensures the contractor has completed all documentation responsibilities before receiving full compensation.

Why the Other Options Are Wrong

Option A: Weekly during construction progress

Weekly submission would be impractical and unnecessary since as-built drawings document final conditions, not ongoing construction progress. Weekly progress is typically documented through progress reports and photos, not formal as-built drawings.

Option B: At the completion of each major construction phase

While some projects may require interim as-built updates at major phases, the standard contractual requirement is for complete as-built drawings at project completion. Submitting at each phase would be incomplete since later phases might affect earlier work.

Option D: Only when specifically requested by the owner

As-built drawings are standard contractual requirements in most construction contracts, not optional deliverables. They are typically specified in the contract documents and required regardless of specific owner requests.

Memory Technique

Think 'AS-BUILT = AFTER BUILT' - these drawings show what was actually constructed, so they can only be completed when construction is finished, right before final payment.

Reference Hint

AIA Contract Documents (A201 General Conditions) Section on Contract Closeout, or Florida Building Code Chapter 1 - Administrative provisions regarding final inspections and occupancy

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing