As-built drawings are typically required to be submitted:
Correct Answer
C) Before final payment and project closeout
As-built drawings are standard deliverables required before final payment and project closeout, documenting the actual constructed conditions for the owner's permanent records.
Why This Is the Correct Answer
As-built drawings are contractually required deliverables that document the final constructed conditions, showing any deviations from the original plans. They serve as permanent record drawings for the owner's facility management and future renovations. These drawings are essential for project closeout and are typically a prerequisite for final payment release. The timing before final payment ensures the contractor has completed all documentation responsibilities before receiving full compensation.
Why the Other Options Are Wrong
Option A: Weekly during construction progress
Weekly submission would be impractical and unnecessary since as-built drawings document final conditions, not ongoing construction progress. Weekly progress is typically documented through progress reports and photos, not formal as-built drawings.
Option B: At the completion of each major construction phase
While some projects may require interim as-built updates at major phases, the standard contractual requirement is for complete as-built drawings at project completion. Submitting at each phase would be incomplete since later phases might affect earlier work.
Option D: Only when specifically requested by the owner
As-built drawings are standard contractual requirements in most construction contracts, not optional deliverables. They are typically specified in the contract documents and required regardless of specific owner requests.
Memory Technique
Think 'AS-BUILT = AFTER BUILT' - these drawings show what was actually constructed, so they can only be completed when construction is finished, right before final payment.
Reference Hint
AIA Contract Documents (A201 General Conditions) Section on Contract Closeout, or Florida Building Code Chapter 1 - Administrative provisions regarding final inspections and occupancy
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass