An electrician needs to service a 480V panel. The electrical source has been de-energized and locked out. What additional step is required before beginning work?
Correct Answer
B) Test the equipment to verify it is de-energized
LOTO procedures require verification that equipment is de-energized through testing before work begins, not just locking out the energy source.
Why This Is the Correct Answer
OSHA's Lockout/Tagout (LOTO) standard (29 CFR 1910.147, applied in construction via 1926.417) requires workers to verify zero energy state by testing the equipment after lockout. A lock on the disconnect does not guarantee de-energization; capacitors, back-feeds, or other stored energy can remain. Testing confirms it is truly safe.
Why the Other Options Are Wrong
Option A: Wait 24 hours for residual energy to dissipate
Waiting 24 hours has no basis in OSHA LOTO requirements. Residual electrical energy in capacitors can be discharged in seconds to minutes with proper procedures; arbitrary wait times are not a recognized safety step.
Option C: Notify all workers on site
Notifying all site workers is a courteous practice and may be required for certain permit systems, but it is not a formal LOTO verification step. Notification alone does not confirm the panel is de-energized.
Option D: Install temporary grounding
Installing temporary grounding is required for some high-voltage transmission work but is not the primary additional step in standard LOTO procedures for a 480V panel. Verification by testing comes first.
Memory Technique
LOTO acronym expanded: Lock Out, Then Operate (test). Before you touch it, prove it is dead. Think of a surgeon confirming anesthesia before cutting β you verify before you proceed.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Calculate the live load capacity required for a 20' Γ 30' office space floor system according to typical IBC requirements.
Next Question
A project requires installation of 850 linear feet of underground utilities. The crew productivity is 95 LF per day with a 5-person crew at $32 per hour each. What is the total labor cost?
