EstatePass
Project MgmtBlueprintshard17% of exam part

An electrical schedule shows a 200-amp main panel feeding four 50-amp subpanels. What is the total connected load capacity?

Correct Answer

A) 200 amps

The total available capacity is limited by the main panel rating of 200 amps, regardless of the sum of subpanel capacities. The main breaker controls the maximum load.

Answer Options
A
200 amps
B
250 amps
C
300 amps
D
400 amps

Why This Is the Correct Answer

The total connected load capacity is limited by the main panel's 200-amp rating, which acts as the bottleneck in the electrical system. Even though the four subpanels have a combined capacity of 200 amps (4 × 50 amps), they cannot exceed what the main panel can supply. The main breaker serves as the primary protection device and determines the maximum available power for the entire system. This is a fundamental principle of electrical load calculations where the weakest link in the chain determines the overall capacity.

Why the Other Options Are Wrong

Option B: 250 amps

250 amps incorrectly assumes you can add some additional capacity beyond the subpanel total, but this ignores the main panel limitation of 200 amps.

Option C: 300 amps

300 amps appears to add some arbitrary additional capacity to the subpanel total, but the main panel's 200-amp limit cannot be exceeded regardless of downstream calculations.

Option D: 400 amps

400 amps incorrectly adds all subpanel capacities (4 × 50 = 200) plus the main panel rating (200), but this double-counts the capacity since the main panel IS the source feeding the subpanels.

Memory Technique

Think 'Main is the Chain' - the main panel is like the narrowest link in a chain, and the whole system can only handle what the main panel allows, regardless of what's downstream.

Reference Hint

NEC Article 220 - Branch-Circuit, Feeder, and Service Load Calculations, and Article 408 - Switchboards and Panelboards

More Project Mgmt Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing