A time and materials contract specifies labor at $85 per hour with a 1.5 multiplier for overtime. If a worker works 45 hours in one week (with 5 hours overtime), what is the total labor charge?

Correct Answer

B) $4,037.50

Regular time: 40 hours × $85 = $3,400. Overtime: 5 hours × $85 × 1.5 = $637.50. Total: $3,400 + $637.50 = $4,037.50.

Answer Options
A
$3,825
B
$4,037.50
C
$4,250
D
$4,462.50

Why This Is the Correct Answer

The calculation correctly separates regular time from overtime hours and applies the appropriate rates. Regular time is calculated as 40 hours × $85 = $3,400, while overtime uses the 1.5 multiplier: 5 hours × $85 × 1.5 = $637.50. The total labor charge is the sum of both: $3,400 + $637.50 = $4,037.50.

Why the Other Options Are Wrong

Option A: $3,825

This answer ($3,825) appears to use an incorrect calculation method, possibly applying a uniform rate without properly accounting for the overtime multiplier of 1.5.

Option C: $4,250

This answer ($4,250) incorrectly applies the overtime multiplier to all 45 hours rather than just the 5 overtime hours, resulting in an overcharge.

Option D: $4,462.50

This answer ($4,462.50) significantly overcharges and likely applies an incorrect multiplier or calculation method to the total hours worked.

Memory Technique

Remember 'ROTO': Regular first (40 hrs), Overtime second (excess hrs), Total multiplier (1.5), Overall sum - always keep regular and overtime separate in your calculations.

Reference Hint

Florida Building Contractor Reference Manual - Contract Administration and Labor Cost Calculations chapter

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing