According to quality control standards, concrete cylinder tests show compressive strength of 2,800 psi when the specification requires 3,000 psi. What should the contractor do?
Correct Answer
B) Investigate the cause and determine corrective action with the engineer
When concrete fails to meet specifications, the contractor must investigate the cause and work with the structural engineer to determine appropriate corrective action, which may include additional testing, structural analysis, or remedial measures.
Why This Is the Correct Answer
When concrete test results fail to meet specifications, the proper protocol requires investigation and engineering consultation. The contractor cannot make unilateral decisions about structural adequacy - this requires professional engineering analysis. The engineer must evaluate whether the reduced strength affects structural integrity and determine if remedial action is needed. This collaborative approach ensures safety and compliance with building codes.
Why the Other Options Are Wrong
Option A: Accept the concrete as it's close to specification
Accepting concrete that doesn't meet specifications violates quality control standards and could compromise structural safety. Even a 200 psi difference (6.7% below spec) could be significant depending on the structural application and safety factors.
Option C: Order new concrete immediately
Ordering new concrete immediately is premature without proper investigation. The existing concrete may be salvageable through various remedial measures, and hasty replacement could be costly and unnecessary.
Option D: Add fiber reinforcement to compensate
Adding fiber reinforcement cannot compensate for inadequate compressive strength and would require engineering approval. Fibers primarily improve tensile strength and crack control, not compressive strength deficiencies.
Memory Technique
Think 'INVESTIGATE before you COMPENSATE' - when concrete fails tests, investigation with engineering consultation comes before any corrective measures.
Reference Hint
ACI 318 Building Code Requirements for Structural Concrete, Chapter 26 - Quality Control and Testing
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A framing crew's productivity decreases from 1,000 board feet per day to 750 board feet per day when working in cold weather. If the crew cost is $2,400 per day, what is the increased labor cost per board foot due to weather?
Next Question
For a $2.8 million commercial construction project in Florida, what is the typical range for a construction contingency allowance?