According to Florida Statute 489, what is the minimum experience requirement for a General Contractor license?
Correct Answer
B) 4 years of experience in the construction industry
Florida Statute 489 requires a minimum of 4 years of experience in the construction industry for General Contractor licensure. This experience must be verified and documented.
Why This Is the Correct Answer
Florida Statute 489.111 specifically mandates that applicants for a General Contractor license must possess a minimum of 4 years of verifiable experience in the construction industry. This experience requirement is designed to ensure that contractors have sufficient practical knowledge and skills before being granted the authority to oversee construction projects. The experience must be documented and verified through employment records, project documentation, or other acceptable proof. This 4-year requirement distinguishes General Contractors from other license types that may have different experience thresholds.
Why the Other Options Are Wrong
Option A: 2 years of experience in the construction industry
2 years is insufficient under Florida Statute 489 and does not meet the minimum experience threshold established for General Contractor licensure.
Option C: 3 years of experience in the construction industry
3 years falls short of the statutory requirement and would not qualify an applicant for General Contractor licensure under Florida law.
Option D: 5 years of experience in the construction industry
5 years exceeds the minimum requirement, and while having 5 years would qualify someone, it is not the minimum threshold established by the statute.
Memory Technique
Use the mnemonic 'Four Corners of Florida' - General Contractors need 4 years to work in all four corners of the state
Reference Hint
Florida Statute 489.111 - Qualifications for licensure; Chapter 61G4 Florida Administrative Code for detailed licensing requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
An indemnification clause in a construction contract typically requires one party to:
Next Question
A project has the following activities: A (5 days), B (3 days), C (7 days), D (4 days). Activities A and B can start immediately. Activity C depends on A completion. Activity D depends on both B and C completion. What is the critical path duration?