EstatePass
Contract AdminContractseasy40% of exam part

According to Florida Chapter 713, how long does a contractor have to file a Claim of Lien after the last day of work?

Correct Answer

C) 90 days

Under Florida Statute Chapter 713, a Claim of Lien must be recorded within 90 days of the last day the lienor performed work or furnished materials to the project.

Answer Options
A
30 days
B
60 days
C
90 days
D
120 days

Why This Is the Correct Answer

Florida Statute Chapter 713.13 specifically states that a Claim of Lien must be recorded within 90 days after the final furnishing of labor, services, or materials by the lienor. This 90-day period is a strict statutory deadline that cannot be extended. The timeframe begins from the last day the contractor performed work or provided materials, not from the completion of the entire project. Missing this deadline results in the complete loss of lien rights.

Why the Other Options Are Wrong

Option A: 30 days

30 days is too short and not the statutory requirement under Florida Chapter 713

Option B: 60 days

60 days is insufficient time under Florida lien law requirements

Option D: 120 days

120 days exceeds the statutory deadline and would result in loss of lien rights

Memory Technique

Think '90 days to save your pay' - the 90-day rule protects your right to payment through lien rights

Reference Hint

Florida Statutes Chapter 713.13 - Construction Liens

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing