According to Florida Building Code requirements, as-built drawings for commercial projects must be submitted to the building department within how many days of receiving the certificate of occupancy?
Correct Answer
A) 30 days
The Florida Building Code requires as-built drawings for commercial projects to be submitted to the building department within 30 days of receiving the certificate of occupancy to maintain accurate records.
Why This Is the Correct Answer
The Florida Building Code specifically mandates that as-built drawings for commercial projects must be submitted within 30 days of receiving the certificate of occupancy. This requirement ensures that the building department maintains current and accurate records of the final construction details. The 30-day timeframe provides sufficient time for contractors to compile the necessary documentation while ensuring timely submission. This is a critical compliance requirement that contractors must meet to avoid potential penalties or issues with future permits.
Why the Other Options Are Wrong
Option B: 60 days
60 days exceeds the required timeframe established by the Florida Building Code. While this might seem like a reasonable amount of time, the code specifically requires submission within 30 days, making this option incorrect.
Option C: 90 days
90 days is far too long according to Florida Building Code requirements. This extended timeframe would delay the building department's ability to maintain current records and could impact future inspections or modifications to the building.
Option D: As-built drawings are not required to be submitted
This is incorrect because as-built drawings are indeed required for commercial projects under the Florida Building Code. The submission of these drawings is mandatory, not optional, and serves important documentation and safety purposes.
Memory Technique
Think '30 days to document the commercial way' - commercial projects need as-built drawings submitted within 30 days of CO (Certificate of Occupancy)
Reference Hint
Florida Building Code, Chapter 1, Section 107 - Submittal Documents and Section 110 - Certificate of Occupancy requirements
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A contractor estimates that 2,500 linear feet of electrical conduit installation will require 125 labor hours. What is the productivity rate in linear feet per hour?
Next Question
In CPM scheduling, if an activity has an early start of day 10, duration of 5 days, and late finish of day 20, what is the activity's total float?