EstatePass
Contract AdminContractsmedium40% of exam part

According to AIA Document A201, when must the contractor provide written notice to the architect of any claim for additional time or money?

Correct Answer

B) Within 21 days after occurrence of the event giving rise to the claim

AIA A201 requires contractors to provide written notice of claims within 21 days after the occurrence of the event or first observance of the condition giving rise to the claim. This timely notice requirement is critical for preserving claim rights.

Answer Options
A
Within 10 days after occurrence of the event giving rise to the claim
B
Within 21 days after occurrence of the event giving rise to the claim
C
Within 30 days after occurrence of the event giving rise to the claim
D
Before substantial completion of the project

Why This Is the Correct Answer

AIA Document A201, General Conditions of the Contract for Construction, specifically requires contractors to provide written notice of claims for additional time or money within 21 days after the occurrence of the event or first observance of the condition giving rise to the claim. This 21-day notice requirement is a critical procedural safeguard that protects both parties by ensuring timely communication of potential claims. Failure to provide this notice within the specified timeframe can result in waiver of the contractor's right to pursue the claim. This requirement allows the architect and owner to investigate the claim while the facts are fresh and potentially mitigate damages.

Why the Other Options Are Wrong

Option A: Within 10 days after occurrence of the event giving rise to the claim

10 days is too short a timeframe and is not the requirement specified in AIA A201. While some contracts may have shorter notice periods, the standard AIA A201 document specifically requires 21 days.

Option C: Within 30 days after occurrence of the event giving rise to the claim

30 days is longer than the actual requirement in AIA A201. While this might seem like a reasonable timeframe, the document specifically requires notice within 21 days, not 30 days.

Option D: Before substantial completion of the project

This option is far too vague and extends the notice period unreasonably. Substantial completion could occur months or years after the claim-triggering event, which would defeat the purpose of timely notice and make claim investigation and resolution much more difficult.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing