EstatePass
Contract AdminProceduresmedium13% of exam part

A project has activities with the following durations: A(5 days), B(8 days), C(3 days), D(6 days). Path 1: A-C = 8 days, Path 2: B-D = 14 days. What is the total float for Path 1?

Correct Answer

C) 6 days

Total float is calculated as the difference between the critical path duration (14 days) and the path duration (8 days). Therefore, Path 1 has 6 days of total float.

Answer Options
A
0 days
B
3 days
C
6 days
D
8 days

Why This Is the Correct Answer

Total float represents the amount of time an activity or path can be delayed without affecting the project completion date. It is calculated by subtracting the path duration from the critical path duration. Since Path 2 (B-D) takes 14 days and is the critical path, and Path 1 (A-C) takes only 8 days, Path 1 has 6 days of float (14 - 8 = 6). This means Path 1 can be delayed by up to 6 days without impacting the overall project schedule.

Why the Other Options Are Wrong

Option A: 0 days

0 days would indicate that Path 1 is on the critical path with no flexibility for delays, but Path 1 is not the critical path since it's shorter than Path 2.

Option B: 3 days

3 days appears to be an arbitrary number that doesn't result from the proper calculation of critical path duration minus path duration.

Option D: 8 days

8 days is the duration of Path 1 itself, not the float calculation. Float is the difference between critical path and current path, not the path duration.

Memory Technique

Remember 'FLOAT = LONGEST - CURRENT' - the float is always the difference between the longest (critical) path and your current path duration.

Reference Hint

Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing