During contract closeout, the architect issues a Certificate of Substantial Completion. A subcontractor discovers a defect in their work 8 months later. The owner demands the general contractor fix the defect immediately. What is the contractor's best course of action?
Correct Answer
C) Review the warranty provisions and fix the defect if still under warranty
Substantial completion does not eliminate warranty obligations. The contractor should review the contract's warranty provisions to determine if the defect falls within the warranty period and respond accordingly.
Why This Is the Correct Answer
Option C is correct because substantial completion and warranty obligations are separate contractual concepts. The Certificate of Substantial Completion marks when the project is ready for its intended use, but it does not terminate the contractor's warranty responsibilities. The contractor must review the specific warranty provisions in the contract to determine the warranty period, scope of coverage, and proper response to defect claims. This approach ensures compliance with contractual obligations while protecting the contractor's rights.
Why the Other Options Are Wrong
Option A: Refuse to fix it since substantial completion has passed
Option A is incorrect because substantial completion does not eliminate warranty obligations. The Certificate of Substantial Completion addresses project readiness for use, but warranty periods typically begin at substantial completion and extend for a specified duration (commonly one year). Refusing to address warranty claims based solely on substantial completion being achieved demonstrates a misunderstanding of these distinct contractual phases.
Option B: Fix the defect and bill the owner for the work
Option B is incorrect because if the defect falls within the warranty period and scope, the contractor is contractually obligated to remedy it at no cost to the owner. Billing the owner for warranty work would constitute a breach of contract. The contractor should only charge for work that falls outside warranty coverage or for improvements beyond the original scope.
Option D: Demand the subcontractor fix it at their own expense
Option D is incorrect because while the subcontractor may ultimately be responsible for the defect, the general contractor has a direct contractual relationship with the owner and cannot simply demand the subcontractor handle it. The contractor must first fulfill their warranty obligations to the owner, then pursue remedies against the subcontractor through their separate subcontract agreement.
Memory Technique
Think 'SWaP' - Substantial completion starts Warranty Period. The certificate doesn't eliminate responsibilities, it triggers new timeline phases.
Reference Hint
AIA A201 General Conditions, Section 12 - Uncovering and Correction of Work, and Section 9.8 - Substantial Completion procedures
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass