Contract AdminContractseasy40% of exam part

Under a unit price contract, concrete work is priced at $145 per cubic yard. The original estimate was 850 cubic yards, but actual placement was 920 cubic yards. What is the total payment due for concrete work?

Correct Answer

B) $133,400

In a unit price contract, payment is based on actual quantities placed, not estimated quantities. Total payment = 920 cubic yards × $145 per cubic yard = $133,400.

Answer Options
A
$123,250
B
$133,400
C
$140,500
D
$145,000

Why This Is the Correct Answer

Under a unit price contract, payment is always based on the actual quantities of work performed, not the original estimated quantities. This is a fundamental principle of unit price contracts where the contractor assumes the risk of quantity variations. The calculation is straightforward: multiply the actual quantity placed (920 cubic yards) by the unit price ($145 per cubic yard) to get $133,400. This protects both parties by ensuring payment reflects the actual work completed.

Why the Other Options Are Wrong

Option A: $123,250

This amount ($123,250) appears to be calculated using an incorrect quantity or rate, possibly mixing up numbers from the problem or applying an incorrect calculation method.

Option C: $140,500

This amount ($140,500) doesn't correspond to any logical calculation using the given numbers and appears to be a distractor answer.

Option D: $145,000

This amount ($145,000) incorrectly uses 1,000 cubic yards instead of the actual 920 cubic yards placed, showing a fundamental misunderstanding of unit price contract principles.

Memory Technique

Remember 'ACTUAL = PAYMENT' for unit price contracts. The estimate is just for bidding; you always get paid for what you actually install.

Reference Hint

Florida Building Construction Standards - Chapter on Contract Types and Payment Methods, specifically the section covering Unit Price Contracts

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing