In a dispute resolution clause that specifies mediation followed by arbitration, what happens if mediation fails to resolve the dispute?
Correct Answer
C) The dispute proceeds to binding arbitration
When a contract specifies a tiered dispute resolution process of mediation followed by arbitration, failure of mediation triggers the next step, which is binding arbitration. This process avoids court litigation while providing a final resolution mechanism.
Why This Is the Correct Answer
In a tiered dispute resolution clause specifying mediation followed by arbitration, the contract creates a binding sequence of steps. When mediation fails to resolve the dispute, the parties are contractually obligated to proceed to the next specified step, which is binding arbitration. This creates a complete alternative dispute resolution process that avoids court litigation while ensuring final resolution. The arbitration becomes the final and binding mechanism for resolving the dispute.
Why the Other Options Are Wrong
Option A: The parties must proceed to litigation in court
This is incorrect because the contract specifically establishes arbitration as the next step, not court litigation. The parties have contractually agreed to avoid court proceedings by using the tiered ADR process.
Option B: The parties must attempt a second mediation with a different mediator
This is incorrect because the contract doesn't typically require multiple mediation attempts with different mediators. Once mediation fails, the process moves to the next contractually specified step, which is arbitration.
Option D: The contract is void and parties must negotiate a new agreement
This is incorrect because mediation failure doesn't void the contract. The dispute resolution clause is designed to handle such failures by providing the next step (arbitration), and the underlying contract remains valid.
Memory Technique
Think 'M-A-C': Mediation fails β Arbitration next β Court avoided. The tiered system keeps you out of court by providing the next contractual step.
Reference Hint
Florida Construction Law and Contract Administration chapter on Alternative Dispute Resolution (ADR) and contract dispute resolution clauses
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass