A scaffold is being erected for a multi-story building project. The scaffold is 125 feet in height. How often must this scaffold be inspected by a competent person?

Correct Answer

D) Both A and C

OSHA requires scaffolds to be inspected by a competent person daily before each work shift and after any occurrence that could affect the scaffold's structural integrity, such as high winds, earthquakes, or impacts.

Answer Options
A
Daily before each work shift
B
Weekly
C
After any occurrence that could affect structural integrity
D
Both A and C

Why This Is the Correct Answer

OSHA 29 CFR 1926.451(f)(3) requires scaffolds to be inspected by a competent person before each work shift and after any occurrence that could affect the scaffold's structural integrity. This dual requirement ensures both routine safety checks and event-driven inspections. The height of 125 feet makes this a high-risk scaffold that demands the most stringent inspection protocols. Both daily inspections and post-incident inspections are mandatory requirements, not alternatives.

Why the Other Options Are Wrong

Option A: Daily before each work shift

This is partially correct but incomplete - it only addresses the daily inspection requirement while ignoring the equally important post-incident inspection requirement.

Option B: Weekly

Weekly inspections are insufficient for scaffold safety requirements. OSHA mandates daily inspections, not weekly ones, especially for scaffolds of this height.

Option C: After any occurrence that could affect structural integrity

This is partially correct but incomplete - it only addresses post-incident inspections while ignoring the mandatory daily inspection requirement before each work shift.

Memory Technique

Think 'DAILY + DAMAGE' - scaffolds need Daily inspections plus inspections after any Damage or incident that could affect structural integrity.

Reference Hint

OSHA Construction Standards 29 CFR 1926 Subpart L - Scaffolds, specifically section 1926.451(f)(3) for inspection requirements