EstatePass
Project MgmtSafetymedium20% of exam part

A renovation project involves disturbing lead-based paint in a residential building built in 1955. What is the maximum allowable airborne lead concentration for construction workers?

Correct Answer

B) 50 μg/m³

OSHA's lead standard for construction sets the permissible exposure limit (PEL) at 50 micrograms per cubic meter (μg/m³) as an 8-hour time-weighted average for airborne lead exposure.

Answer Options
A
30 μg/m³
B
50 μg/m³
C
100 μg/m³
D
200 μg/m³

Why This Is the Correct Answer

OSHA's lead standard for construction sets the permissible exposure limit (PEL) at 50 micrograms per cubic meter (μg/m³) as an 8-hour time-weighted average for airborne lead exposure.

More Project Mgmt Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing