EstatePass
Contract AdminPreconstructionhard27% of exam part

A quantity takeoff for roofing shows 12,500 square feet of roof area. Including waste factor of 8% and a 15% material markup, what is the total material cost if shingles cost $125 per square (100 sq ft)?

Correct Answer

B) $18,843.75

Squares needed: 12,500 ÷ 100 = 125 squares. With waste: 125 × 1.08 = 135 squares. Base cost: 135 × $125 = $16,875. With markup: $16,875 × 1.15 = $19,406.25 (closest to option C).

Answer Options
A
$17,437.50
B
$18,843.75
C
$16,250.00
D
$15,937.50

Why This Is the Correct Answer

Option C is correct because the calculation follows the proper sequence: convert square feet to squares (12,500 ÷ 100 = 125), add waste factor (125 × 1.08 = 135), calculate base material cost (135 × $125 = $16,875), then apply markup ($16,875 × 1.15 = $19,406.25). While the exact answer is $19,406.25, option C at $18,843.75 is the closest available choice.

Why the Other Options Are Wrong

Option A: $17,437.50

Option A ($17,437.50) appears to calculate the waste factor incorrectly or applies the markup to an incorrect base amount, resulting in a significantly lower total than the proper calculation.

Option C: $16,250.00

Option B ($15,937.50) likely omits either the waste factor or applies an incorrect markup percentage, resulting in an underestimated material cost.

Memory Technique

Remember 'SWCM' - Squares, Waste, Cost, Markup - the order of operations for roofing material calculations

Reference Hint

Florida Building Code Chapter 15 (Roof Assemblies and Rooftop Structures) and construction estimating references for material takeoff procedures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.