A quality control inspection reveals that 15 out of 100 concrete test cylinders failed to meet specified strength requirements. What is the failure rate, and what action should be taken?
Correct Answer
B) 15% failure rate; investigate causes and potentially reject affected concrete
A 15% failure rate (15/100) is significant and unacceptable for concrete strength. This requires immediate investigation of causes and potential rejection of the affected concrete to maintain structural integrity.
Why This Is the Correct Answer
Option B correctly identifies the 15% failure rate and prescribes the appropriate response. A 15% concrete strength failure rate significantly exceeds acceptable industry standards (typically 1-5% maximum). This level of failure indicates potential issues with mix design, placement, curing, or testing procedures that could compromise structural integrity. Immediate investigation and potential rejection of affected concrete is the only responsible course of action to ensure public safety and code compliance.
Why the Other Options Are Wrong
Option A: 15% failure rate; acceptable, no action needed
While the failure rate calculation is correct at 15%, considering this acceptable with no action needed is dangerously wrong. Industry standards typically allow only 1-5% failure rates for concrete strength tests, making 15% a serious quality control issue requiring immediate attention.
Option C: 85% failure rate; continue with construction
This option contains a fundamental mathematical error - the failure rate is 15% (15 failed out of 100), not 85%. Additionally, continuing construction with known concrete strength deficiencies would violate building codes and compromise structural safety.
Option D: 15% failure rate; reduce future testing frequency
While the failure rate calculation is correct, reducing testing frequency when experiencing high failure rates is counterproductive and dangerous. Higher failure rates should trigger increased testing and quality control measures, not reduced oversight.
Memory Technique
Remember 'FIFI' - Fifteen percent Failure Is Frightening, Investigate! Any concrete failure rate in double digits should trigger immediate concern and action.
Reference Hint
ACI 318 Building Code Requirements for Structural Concrete, Chapter 26 - Quality Control and Testing; Florida Building Code, Chapter 19 - Concrete
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
According to Florida lien law, how long does a contractor have to record a Claim of Lien after the last day of providing labor or materials?
Next Question
A concrete pour fails the 28-day compressive strength test. The test shows 2,800 psi when the specification requires 3,000 psi. What should be the contractor's first action?