A quality control checklist for concrete placement should include verification of all the following EXCEPT:
Correct Answer
C) Final project budget reconciliation
Quality control checklists focus on technical construction requirements. Budget reconciliation is a project management function, not a quality control item for concrete placement.
Why This Is the Correct Answer
Quality control checklists for concrete placement focus exclusively on technical construction requirements that directly affect the structural integrity and performance of the concrete. Budget reconciliation is a financial management activity that belongs to project administration, not quality control. Quality control is concerned with ensuring the concrete meets specifications for strength, durability, and proper installation, while budget matters are handled separately by project management personnel.
Why the Other Options Are Wrong
Option A: Proper slump and air content testing
This is a critical quality control item - slump testing verifies workability and water content, while air content testing ensures proper freeze-thaw resistance and workability.
Option B: Adequate reinforcement placement and cover
This is essential for quality control - proper reinforcement placement and adequate concrete cover are crucial for structural integrity and corrosion protection.
Option D: Appropriate curing procedures and protection
This is a vital quality control requirement - proper curing procedures and protection ensure the concrete achieves specified strength and durability characteristics.
Memory Technique
Think 'SCAR' for concrete QC: Slump/air content, Cover/reinforcement, Appropriate curing, Reject budget items
Reference Hint
ACI 301 - Specifications for Structural Concrete, Chapter on Quality Control and Inspection
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass