EstatePass
Contract AdminPreconstructioneasy27% of exam part

A project specification requires the contractor to include a $15,000 allowance for plumbing fixtures. During construction, the owner selects fixtures costing $18,500. Who is responsible for the $3,500 difference?

Correct Answer

D) The owner pays the additional cost as a change order

When actual costs exceed established allowances, the difference is typically handled as a change order with the owner responsible for additional costs above the allowance amount.

Answer Options
A
The cost is split equally between owner and contractor
B
The architect is responsible for the overage
C
The contractor must absorb the additional cost
D
The owner pays the additional cost as a change order

Why This Is the Correct Answer

Allowances in construction contracts are predetermined amounts allocated for specific items where exact costs are unknown at contract signing. When the owner selects items that exceed the allowance amount, this creates a scope change from the original contract terms. The contractor has fulfilled their obligation by providing the allowance amount, and any overage becomes the owner's responsibility through the change order process, which is the standard mechanism for handling cost variations in construction contracts.

Why the Other Options Are Wrong

Option A: The cost is split equally between owner and contractor

The contractor is not responsible for absorbing costs above the allowance because they have already allocated the specified $15,000 as required by the contract. Requiring contractors to absorb overages would make allowances meaningless and create unfair financial risk.

Option C: The contractor must absorb the additional cost

The architect has no financial responsibility for allowance overages. Their role is design and specification, not cost coverage. The owner's selection decision, not architectural error, caused the overage.

Memory Technique

Think 'Allowance = Contractor's Limit, Overage = Owner's Bill' - the contractor's financial responsibility stops at the allowance amount

Reference Hint

Look up 'Allowances and Unit Prices' in contract administration chapters, or 'Change Orders' sections in construction law references

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.