A project site contains a protected gopher tortoise habitat. Construction cannot begin until the tortoises are relocated by a licensed wildlife specialist at a cost of $850 per tortoise. If 17 tortoises must be relocated and the relocation permit costs $2,400, what is the total wildlife compliance cost?
Correct Answer
B) $16,850
Relocation costs: 17 tortoises × $850 = $14,450. Total cost: $14,450 + $2,400 permit fee = $16,850.
Why This Is the Correct Answer
Option B correctly calculates the total wildlife compliance cost by adding both required components: the relocation cost for 17 tortoises at $850 each ($14,450) plus the mandatory permit fee of $2,400. This gives the complete total of $16,850, which includes all costs necessary to comply with wildlife protection regulations before construction can legally begin.
Why the Other Options Are Wrong
Option A: $14,450
Option A only includes the tortoise relocation costs (17 × $850 = $14,450) but fails to add the required permit fee of $2,400. This represents an incomplete calculation that would leave the contractor short of the actual total compliance cost.
Option D: $12,050
Option C appears to be a miscalculation that doesn't properly account for either the correct number of tortoises or the proper cost per tortoise, resulting in a figure that's significantly lower than the actual required compliance costs.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
