A project schedule shows Activity X has an early start of day 15, early finish of day 22, late start of day 18, and late finish of day 25. What is the total float for this activity?

Correct Answer

D) 3 days

Total float is calculated as Late Start minus Early Start (18 - 15 = 3 days) or Late Finish minus Early Finish (25 - 22 = 3 days).

Answer Options
A
7 days
B
10 days
C
15 days
D
3 days

Why This Is the Correct Answer

Total float represents the amount of time an activity can be delayed without affecting the project completion date. It is calculated using either Late Start minus Early Start (18 - 15 = 3 days) or Late Finish minus Early Finish (25 - 22 = 3 days). Both calculations yield the same result of 3 days, confirming that Activity X has 3 days of scheduling flexibility before it impacts the critical path.

Why the Other Options Are Wrong

Option A: 7 days

7 days incorrectly represents the duration of the activity (Early Finish minus Early Start: 22 - 15 = 7). This is the activity duration, not the total float. Students often confuse activity duration with float calculations.

Option B: 10 days

10 days appears to be an arbitrary calculation that doesn't follow any standard float formula. This might result from incorrectly adding values or misunderstanding the relationship between early and late dates in project scheduling.

Option C: 15 days

15 days represents the Early Start date itself, not a calculated float value. This shows confusion between schedule dates and float calculations, possibly mixing up the Early Start value with the actual float computation.

Memory Technique

Remember 'LESE' - Late minus Early = Slack/float. Whether using Start dates (LS - ES) or Finish dates (LF - EF), both give the same total float value.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.