A project schedule shows Activity A (4 days) must finish before Activity B (6 days) can start, and Activity B must finish before Activity C (3 days) can start. If Activity A starts on Day 1, what is the earliest finish date for Activity C?
Correct Answer
A) Day 13
Activity A: Days 1-4, Activity B: Days 5-10, Activity C: Days 11-13. Activity C finishes on Day 13, making it the earliest finish date for the sequence.
Why This Is the Correct Answer
This is a sequential scheduling problem where activities must be completed in order with finish-to-start relationships. Activity A runs from Day 1-4 (4 days), Activity B starts immediately after A finishes and runs from Day 5-10 (6 days), and Activity C starts immediately after B finishes and runs from Day 11-13 (3 days). The earliest finish date for Activity C is therefore Day 13.
Why the Other Options Are Wrong
Option B: Day 14
Day 14 would be incorrect because it adds an extra day beyond the required sequence. This might result from incorrectly counting days or adding unnecessary buffer time between activities.
Option C: Day 10
Day 10 is when Activity B finishes, not Activity C. This error occurs when someone stops calculating after Activity B and forgets to add Activity C's duration.
Option D: Day 12
Day 12 falls one day short of the actual finish date. This error typically occurs from miscounting the days in one of the activities or incorrectly calculating the start/finish relationships.
Memory Technique
Use the acronym 'ADD' - Always Draw Diagrams for scheduling problems, and remember that finish-to-start means the next activity starts the day AFTER the previous one finishes.
Reference Hint
Project Management chapter covering Critical Path Method (CPM) and activity scheduling relationships
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Previous Question
A LEED project requires that 75% of construction waste be diverted from landfills. The project generated 240 tons of waste, and 185 tons were recycled or reused. Does this meet the LEED requirement?
Next Question
When performing a quantity takeoff for framing lumber, what is the standard waste factor typically applied?