EstatePass
Contract AdminPermitsmedium20% of exam part

A project requires work in a wetland area that will impact 0.8 acres. The mitigation banking fee is $45,000 per acre, and additional permit processing fees total $3,200. What is the total environmental permit cost?

Correct Answer

B) $39,200

The mitigation cost is 0.8 acres × $45,000 = $36,000, plus $3,200 in processing fees, totaling $39,200 for the environmental permits.

Answer Options
A
$48,200
B
$39,200
C
$45,000
D
$36,000

Why This Is the Correct Answer

Option B is correct because it includes both components of environmental permit costs. The mitigation banking fee must be calculated by multiplying the impacted acreage (0.8 acres) by the per-acre fee ($45,000), which equals $36,000. This mitigation cost must then be added to the additional permit processing fees of $3,200, resulting in a total environmental permit cost of $39,200.

Why the Other Options Are Wrong

Option A: $48,200

Option C represents only the per-acre mitigation banking fee ($45,000) without accounting for the actual impacted acreage (0.8 acres) or the additional processing fees, making it an incorrect calculation.

Option C: $45,000

Option A only accounts for the mitigation banking fee ($36,000) but fails to include the additional permit processing fees of $3,200, making it an incomplete calculation of the total environmental permit cost.

Memory Technique

Remember 'MAT' - Mitigation (per acre × actual acres) + Administrative fees + Total = complete environmental permit cost

Reference Hint

Florida Building Code Chapter 1 - Administrative provisions, or Environmental regulations section covering wetland mitigation requirements and permit fee structures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.