A project requires 850 cubic yards of fill material with 95% compaction. If the soil has a shrinkage factor of 15%, how many cubic yards of loose soil must be hauled to the site?
Correct Answer
D) 1000 cubic yards
With 15% shrinkage, you need 850 ÷ 0.85 = 1000 cubic yards of loose soil to achieve 850 cubic yards of compacted fill at 95% compaction.
Why This Is the Correct Answer
When soil is compacted, it shrinks by 15%, meaning the final compacted volume is only 85% of the original loose volume. To find the required loose soil volume, we divide the needed compacted volume by the compaction factor (0.85). The calculation is 850 ÷ 0.85 = 1000 cubic yards. The 95% compaction requirement is already factored into the 850 cubic yards specified, so we only need to account for the 15% shrinkage.
Why the Other Options Are Wrong
Option A: 722.5 cubic yards
This answer incorrectly multiplies 850 by 0.85 instead of dividing by 0.85, which would give you less material than needed rather than accounting for the shrinkage that requires more loose material.
Option B: 850 cubic yards
This answer ignores the shrinkage factor entirely, assuming that 850 cubic yards of loose soil will yield 850 cubic yards of compacted fill, which is incorrect when there's a 15% shrinkage.
Option C: 977.5 cubic yards
This answer incorrectly adds 15% to the required volume (850 × 1.15), which is the wrong mathematical approach for dealing with shrinkage factors in soil compaction calculations.
Memory Technique
Remember 'Shrinkage = Shortage' - when soil shrinks, you have a shortage, so you need to START with more loose material. Always divide by the remaining percentage (100% - shrinkage%).
Reference Hint
Look up soil compaction and earthwork calculations in Chapter 7 (Site Work) or the earthwork section of your construction reference manual.
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
A detail drawing shows a scale of 3/4" = 1'-0". If a dimension measures 2.25 inches on the drawing, what is the actual dimension?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Previous Question
During construction, you receive shop drawings for structural steel that differ from the original design drawings. What is the appropriate first step?
Next Question
A construction supervisor discovers that workers are not wearing required hard hats in an area with overhead hazards. According to OSHA, what type of PPE violation is this?