EstatePass
Contract AdminPermitsmedium20% of exam part

A project impacts 1.2 acres of wetlands. Mitigation banking costs $52,000 per acre, permit application fees are $2,800, and monitoring fees are $8,500. What is the total environmental permit cost?

Correct Answer

B) $73,700

Total cost is (1.2 acres × $52,000) + $2,800 + $8,500 = $62,400 + $2,800 + $8,500 = $73,700 for all environmental permit requirements.

Answer Options
A
$62,400
B
$73,700
C
$82,200
D
$71,700

Why This Is the Correct Answer

Option C is correct because it properly calculates all three components of environmental permit costs. The calculation includes mitigation banking costs (1.2 acres × $52,000 = $62,400), plus the permit application fees ($2,800), plus monitoring fees ($8,500). When all three costs are added together, the total environmental permit cost equals $73,700.

Why the Other Options Are Wrong

Option A: $62,400

Option D overestimates the total cost, possibly by miscalculating the mitigation banking cost or incorrectly adding additional fees not specified in the problem.

Option C: $82,200

Option A only includes the mitigation banking cost ($62,400) and fails to add the permit application fees and monitoring fees, resulting in an incomplete total.

Memory Technique

Remember 'MAP' - Mitigation (per acre), Application (flat fee), Plus monitoring (flat fee) - all three must be included in total environmental costs.

Reference Hint

Florida Building Code Chapter 1, Environmental Regulations section, or DEP permit fee schedules in the reference materials

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.