A project has the following activities: A (5 days), B (3 days), C (7 days), D (4 days). Activities A and B can start immediately. Activity C depends on A completion. Activity D depends on both B and C completion. What is the critical path duration?

Correct Answer

C) 16 days

The critical path is A→C→D (5+7+4=16 days). The alternative path B→D (3+4=7 days) plus waiting for C completion still results in 16 days total project duration.

Answer Options
A
12 days
B
14 days
C
16 days
D
19 days

Why This Is the Correct Answer

The critical path is the longest sequence of dependent activities that determines the minimum project duration. Path A→C→D takes 5+7+4=16 days, which is longer than any other possible path. Since activity D cannot start until both B and C are complete, and C depends on A, the project cannot finish in less than 16 days regardless of when B completes.

Why the Other Options Are Wrong

Option A: 12 days

12 days would only account for activities A and C (5+7=12), but ignores that activity D still needs 4 additional days to complete after C finishes.

Option B: 14 days

14 days incorrectly assumes some overlap or parallel processing that isn't possible given the dependencies, or miscalculates the sequential durations of the critical path activities.

Option D: 19 days

19 days would incorrectly add all activity durations (5+3+7+4=19) without recognizing that activities A and B can run in parallel, not sequentially.

Memory Technique

Remember 'Longest Path Wins' - the critical path is always the longest sequence of activities, and you can't finish the project any faster than this path allows.

Reference Hint

Look up 'Critical Path Method (CPM)' or 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing