A project has liquidated damages of $500 per day for delays. The project is completed 12 days late due to weather delays (8 days) and contractor delays (4 days). What is the contractor's liability for liquidated damages?

Correct Answer

A) $2,000

Liquidated damages typically apply only to delays caused by the contractor, not force majeure events like weather. Therefore, only the 4 contractor-caused delay days apply: 4 days × $500 = $2,000.

Answer Options
A
$2,000
B
$6,000
C
$4,000
D
$0

Why This Is the Correct Answer

Liquidated damages are contractual penalties that apply only to delays caused by the contractor's actions or negligence. Weather delays are considered force majeure events or acts of God, which are typically beyond the contractor's control and therefore excluded from liquidated damage calculations. Only the 4 days of contractor-caused delays are subject to the $500 per day penalty, resulting in $2,000 in liquidated damages.

Why the Other Options Are Wrong

Option B: $6,000

Option D incorrectly applies liquidated damages to all 12 days of delay (12 days × $500 = $6,000), including weather delays which are typically excluded as force majeure events.

Option C: $4,000

Option C incorrectly includes only the weather delays (8 days × $500 = $4,000), but weather delays are typically excluded from liquidated damage calculations as force majeure events.

Memory Technique

Remember 'WELD' - Weather Excludes Liquidated Damages. Only contractor-caused delays get 'welded' with penalty fees.

Reference Hint

Florida Building Code Chapter 1, Section 107 - Construction Documents and Permits, or contract law sections covering liquidated damages and force majeure clauses

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.