EstatePass
Contract AdminPreconstructionmedium27% of exam part

A project has an estimated direct cost of $850,000. The owner requires a 15% contingency and the contract includes liquidated damages of $1,500 per day for delays beyond the 180-day completion period. What is the total project budget including contingency?

Correct Answer

A) $977,500

Contingency calculation: $850,000 × 0.15 = $127,500. Total budget: $850,000 + $127,500 = $977,500. Liquidated damages are potential costs, not included in the initial budget.

Answer Options
A
$977,500
B
$1,000,000
C
$1,127,500
D
$1,247,500

Why This Is the Correct Answer

The correct answer is A because the total project budget includes only the direct costs plus the contingency amount. The direct cost of $850,000 multiplied by the 15% contingency rate equals $127,500 in contingency funds. Adding this to the original direct cost gives us $977,500 as the total project budget. Liquidated damages are not included in the initial budget calculation as they represent potential future costs only if delays occur.

Why the Other Options Are Wrong

Option B: $1,000,000

This amount ($1,000,000) appears to be a rounded figure that doesn't match the precise calculation of direct costs plus 15% contingency, which totals $977,500.

Option C: $1,127,500

This amount ($1,127,500) incorrectly includes additional costs beyond the required contingency, possibly mistakenly factoring in liquidated damages or using an incorrect contingency percentage.

Option D: $1,247,500

This amount ($1,247,500) is significantly higher than the correct calculation and likely includes liquidated damages or other costs that should not be part of the initial project budget.

Memory Technique

Remember 'DPC' - Direct costs Plus Contingency only. Liquidated damages are 'Later Damages' - they don't belong in the initial budget calculation.

Reference Hint

Florida Building Construction Standards - Chapter on Project Cost Estimation and Contingency Planning

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing