EstatePass
NASCLAFinancehard15% of exam part

A project has actual costs of $450,000 against a budget of $420,000, with 80% completion. What is the projected cost at completion using the current cost performance?

Correct Answer

A) $562,500

Cost Performance Index (CPI) = Budgeted Cost of Work Performed ÷ Actual Cost = ($420,000 × 0.80) ÷ $450,000 = $336,000 ÷ $450,000 = 0.747. Projected cost at completion = Budget ÷ CPI = $420,000 ÷ 0.747 = $562,500.

Answer Options
A
$562,500
B
$540,000
C
$480,000
D
$525,000

Why This Is the Correct Answer

Option A correctly applies Earned Value Management principles. The Cost Performance Index (CPI) is calculated as Budgeted Cost of Work Performed divided by Actual Cost: ($420,000 × 0.80) ÷ $450,000 = 0.747. The projected cost at completion is then Budget at Completion divided by CPI: $420,000 ÷ 0.747 = $562,500. This assumes current cost performance trends will continue throughout the project.

Why the Other Options Are Wrong

Option B: $540,000

This answer incorrectly assumes the project will finish exactly at budget ($420,000) plus the current overrun ($450,000 - $336,000 = $114,000), totaling $534,000. However, this doesn't account for the poor cost performance continuing through project completion and rounds to $540,000.

Option C: $480,000

This answer appears to simply add the current cost overrun ($30,000) to the original budget ($420,000 + $60,000 = $480,000). This linear projection ignores the Cost Performance Index methodology and doesn't properly account for the deteriorating cost performance trend.

Option D: $525,000

This answer likely uses an incorrect CPI calculation or applies a different forecasting method. It's close to the budget multiplied by 1.25 ($420,000 × 1.25 = $525,000), but doesn't follow the standard EVM formula for estimate at completion using current performance trends.

Memory Technique

Remember 'CPI Predicts Performance': Cost Performance Index = Earned Value ÷ Actual Cost, then Estimate at Completion = Budget ÷ CPI. Poor performance (CPI < 1.0) means higher final costs.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.