A project has activities with the following durations: A(5 days), B(8 days), C(6 days), D(4 days). The network shows A and B can start immediately, C depends on A, and D depends on both B and C. What is the critical path duration?

Correct Answer

B) 15 days

Path 1: A→C→D = 5+6+4 = 15 days. Path 2: B→D = 8+4 = 12 days (but D can't start until both B and C are complete). The critical path is A→C→D at 15 days.

Answer Options
A
13 days
B
15 days
C
17 days
D
23 days

Why This Is the Correct Answer

The critical path is the longest sequence of dependent activities that determines the minimum project duration. Since D depends on both B and C completing, we must wait for both paths to finish before D can start. Path A→C takes 11 days (5+6), while B takes 8 days, so D starts after day 11. The total critical path A→C→D equals 5+6+4 = 15 days.

Why the Other Options Are Wrong

Option A: 13 days

13 days is too short and doesn't account for the full critical path sequence. This might result from incorrectly calculating just A+B (5+8) or missing the dependency relationships.

Option C: 17 days

17 days exceeds the actual critical path duration. This might result from incorrectly adding all activities together or misunderstanding the parallel nature of A and B.

Option D: 23 days

23 days would result from incorrectly adding all four activities in series (5+8+6+4), ignoring that A and B can run in parallel.

Memory Technique

Remember 'LONGEST PATH WINS' - the critical path is always the longest sequence of dependent activities that cannot be shortened without delaying the entire project.

Reference Hint

Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing