A project has activities with the following durations: A(5 days), B(3 days), C(7 days), D(4 days). Path 1: A-B-D = 12 days, Path 2: A-C-D = 16 days. What is the total float for activities on Path 1?
Correct Answer
C) 4 days
Total float is the difference between the critical path duration and the path duration. Path 2 (16 days) is critical, so Path 1 has 16-12 = 4 days of total float.
Why This Is the Correct Answer
Total float represents the amount of time an activity or path can be delayed without affecting the project completion date. The critical path is the longest path through the network, which is Path 2 at 16 days. Path 1 takes 12 days, so it has 16 - 12 = 4 days of total float. This means activities on Path 1 can be delayed up to 4 days without impacting the overall project duration.
Why the Other Options Are Wrong
Option A: 8 days
8 days would be incorrect as it suggests Path 1 has more float than actually exists. This might result from incorrectly calculating the difference or misidentifying which path is critical. The actual float is only 4 days.
Option B: 2 days
2 days is too small and doesn't represent the correct calculation. This might result from subtracting in the wrong direction or making an arithmetic error in the float calculation.
Option D: 0 days
0 days would indicate that Path 1 is also critical, which is incorrect. Only the longest path (Path 2 at 16 days) is critical. Path 1 has slack time available.
Memory Technique
Remember 'FLOAT = CRITICAL - CURRENT': Total float equals the critical path duration minus the current path duration. The longest path floats nothing, shorter paths float the difference.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
