A project has activities A(5 days), B(3 days), C(7 days), and D(4 days). Activities A and B can start immediately. Activity C depends on A, and D depends on B. What is the critical path duration?
Correct Answer
C) 12 days
Path A-C takes 5+7=12 days, while path B-D takes 3+4=7 days. The critical path is A-C with 12 days total duration.
Why This Is the Correct Answer
The critical path is the longest sequence of dependent activities that determines the minimum project duration. In this network, there are two possible paths: A-C (5+7=12 days) and B-D (3+4=7 days). Since A-C takes 12 days and is longer than B-D's 7 days, the critical path duration is 12 days. Any delay in activities A or C will delay the entire project.
Why the Other Options Are Wrong
Option A: 7 days
7 days represents only the duration of path B-D, which is the shorter of the two paths and therefore not the critical path that determines project completion time.
Option B: 19 days
15 days incorrectly adds all activity durations (5+3+7+4=19) or makes an error in path calculation, but activities B and D run parallel to A and C, not in series.
Option D: 15 days
19 days incorrectly assumes all activities run in sequence (5+3+7+4=19), but the network shows A-B are parallel starting activities, not sequential.
Memory Technique
Remember 'LONGEST = CRITICAL' - the critical path is always the longest duration path through the network, as it controls when the project can finish
Reference Hint
Project Management/CPM sections in construction management references, typically found in chapters covering scheduling and critical path method
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass