A project has activities A (5 days), B (3 days), and C (7 days). Activity A must be completed before B starts, and B must be completed before C starts. What is the total project duration using CPM scheduling?
Correct Answer
C) 15 days
Since the activities are sequential (A→B→C), the total project duration is the sum of all activity durations: 5 + 3 + 7 = 15 days. This represents the critical path for this project.
Why This Is the Correct Answer
In CPM scheduling with sequential activities, the total project duration equals the sum of all activity durations along the critical path. Since Activity A must finish before B starts, and B must finish before C starts, there is no overlap or parallel work possible. The critical path is A→B→C, making the total duration 5 + 3 + 7 = 15 days. This represents the longest path through the project network and determines the minimum project completion time.
Why the Other Options Are Wrong
Option A: 7 days
7 days only represents the duration of Activity C alone, which is the longest single activity but not the total project duration when activities must be performed sequentially.
Option B: 12 days
12 days would be the sum of only Activities A and B (5 + 3 + 4 missing days), but this fails to include the full 7-day duration of Activity C that must follow.
Option D: 10 days
10 days is insufficient time to complete all three sequential activities, as it's 5 days short of the required 15 days needed for the complete A→B→C sequence.
Memory Technique
Remember 'Sequential = Sum' - when activities must be done one after another (sequential), the total time is the sum of all individual activity times.
Reference Hint
Look up 'Critical Path Method (CPM)' and 'Project Scheduling' in construction management chapters, typically found in project management or scheduling sections of contractor reference materials.
More Business & Finance Questions
A contractor's license expires on March 31st. If they submit a renewal application on April 15th, what additional requirement must be met under Florida regulations?
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
In Florida, what is the minimum workers' compensation insurance coverage required for construction companies with employees?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
People Also Study
Previous Question
When establishing a contracting business, which professional relationship is typically required for structural modifications to existing buildings?
Next Question
A contractor discovers they need to modify their building permit application after submission. Under Florida regulations, what is the typical timeframe to notify the building department of significant changes?