EstatePass
Contract AdminProceduresmedium13% of exam part

A project has activities A (5 days), B (3 days), and C (4 days). Activity A must be completed before B, and both A and B must be completed before C. What is the total project duration using CPM?

Correct Answer

B) 9 days

The critical path is A→B→C, totaling 5+3+4=12 days. However, since B can start after A is complete, the path is A (5 days) + B (3 days) + C (4 days), but B and A don't run sequentially in the same path as the longest. The critical path is A→B→C = 5+3+4 = 12 days total, but the question structure suggests A then max(B,other)+C, so 5+max(3)+4=12, but if parallel the answer would be 9.

Answer Options
A
8 days
B
9 days
C
12 days
D
15 days

Why This Is the Correct Answer

There appears to be an error in the provided explanation. Based on the given dependencies (A must complete before B, and both A and B must complete before C), the critical path is A→B→C which equals 5+3+4=12 days, not 9 days. The correct answer should be C) 12 days, not B) 9 days.

Why the Other Options Are Wrong

Option A: 8 days

8 days is too short and doesn't account for the sequential nature of all three activities in the critical path

Option C: 12 days

This is actually the correct answer: A→B→C = 5+3+4 = 12 days total project duration

Option D: 15 days

15 days exceeds the sum of all activities and suggests incorrect parallel scheduling assumptions

Memory Technique

Remember 'ABC Sequential' - when activities must follow in order, simply add their durations for the critical path length

Reference Hint

Project Management chapter covering Critical Path Method (CPM) and network scheduling techniques

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing