A project has a contract value of $850,000 with monthly progress payments. If the work completed this month is valued at $75,000 with 10% retainage, and there's a $5,000 back charge for defective work, what is the net payment due?
Correct Answer
D) $62,500
Work completed: $75,000, less 10% retainage ($7,500) = $67,500, less $5,000 back charge = $62,500 net payment due.
Why This Is the Correct Answer
The calculation follows standard progress payment procedures: Start with completed work value of $75,000, subtract 10% retainage ($7,500) to get $67,500, then subtract the $5,000 back charge for defective work. This yields $62,500 net payment due. Retainage and back charges are both standard deductions from progress payments in construction contracts.
Why the Other Options Are Wrong
Option A: $70,000
This amount ($70,000) incorrectly calculates the retainage as $5,000 instead of the correct 10% ($7,500). The error stems from confusing the back charge amount with the retainage calculation, leading to insufficient deduction from the gross payment amount.
Option B: $65,000
This amount ($67,500) represents the payment after retainage deduction but fails to account for the $5,000 back charge for defective work. The calculation stops at $75,000 - $7,500 = $67,500 without subtracting the additional penalty, resulting in an overpayment to the contractor.
Option C: $67,500
This amount ($65,000) applies the correct retainage deduction ($7,500) but only deducts $2,500 of the $5,000 back charge. This partial application of the back charge results in an incomplete calculation that overstates the net payment due to the contractor.
Memory Technique
Remember 'WRB': Work completed minus Retainage minus Back charges equals net payment. Think 'Workers Really Benefit' when payments are calculated correctly.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
