EstatePass
Contract AdminContractseasy40% of exam part

A project has a contract value of $850,000 with 10% retainage. If $680,000 worth of work has been completed and approved, what is the amount due to the contractor?

Correct Answer

C) $612,000

The contractor receives 90% of completed work ($680,000 × 0.90 = $612,000). The remaining 10% ($68,000) is held as retainage until project completion or substantial completion as specified in the contract.

Answer Options
A
$680,000
B
$612,500
C
$612,000
D
$765,000

Why This Is the Correct Answer

With 10% retainage, the contractor receives 90% of completed and approved work. The calculation is straightforward: $680,000 (completed work) × 0.90 = $612,000. The remaining 10% ($68,000) is withheld as retainage until project completion or substantial completion as specified in the contract terms.

Why the Other Options Are Wrong

Option A: $680,000

$680,000 represents the full value of completed work without accounting for retainage. This ignores the 10% retention requirement, which is a standard contract provision to ensure project completion and quality.

Option B: $612,500

$612,500 appears to be a calculation error. This amount doesn't correspond to any logical percentage of the completed work value and suggests incorrect mathematical computation of the retainage calculation.

Option D: $765,000

$765,000 exceeds the completed work value of $680,000, making it mathematically impossible. This suggests confusion about what amount the percentage should be applied to in retainage calculations.

Memory Technique

Remember 'RETAIN 10, PAY 90' - when there's 10% retainage, the contractor gets paid 90% of completed work immediately.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.