EstatePass
Contract AdminContractseasy40% of exam part

A project has a contract value of $500,000 with 10% retainage. The contractor has submitted pay applications totaling $300,000 to date. What is the total amount of retainage being held?

Correct Answer

A) $30,000

Retainage is calculated on the amount of work completed. 10% of $300,000 in completed work equals $30,000 in retainage being held.

Answer Options
A
$30,000
B
$25,000
C
$45,000
D
$50,000

Why This Is the Correct Answer

Retainage is calculated as a percentage of the work completed and invoiced, not the total contract value. The contractor has submitted pay applications totaling $300,000, representing completed work. The retainage rate is 10%, so the amount being held is 10% × $300,000 = $30,000. This retainage will be held until project completion or substantial completion, depending on contract terms.

Why the Other Options Are Wrong

Option B: $25,000

$25,000 would represent a retainage rate of only 8.33% on the completed work ($25,000 ÷ $300,000). This doesn't match the stated 10% retainage rate in the contract. The calculation error likely comes from misapplying percentages or using incorrect base amounts for the retainage calculation.

Option C: $45,000

$45,000 would represent a 15% retainage rate on completed work ($45,000 ÷ $300,000), which exceeds the contract's 10% rate. This error might occur from confusing retainage rates or incorrectly calculating percentages. Florida law typically limits retainage to 10% for private projects and 5% for public projects.

Option D: $50,000

$50,000 represents 10% of the total contract value ($500,000), not the completed work amount. Retainage is only held on work actually completed and invoiced ($300,000), not on the entire contract value. This is a common conceptual error about when retainage applies.

Memory Technique

Remember 'Retainage = Rate × Completed' - retainage is only held on work actually done and invoiced, never on future or unfinished work portions of the contract.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.