EstatePass
NASCLAContractshard15% of exam part

A project has a contract value of $2,500,000 with 10% retainage held until 50% completion, then reduced to 5%. If the project is 75% complete, what is the total amount of retainage being held?

Correct Answer

A) $156,250

At 50% completion: $1,250,000 × 10% = $125,000 retainage. From 50% to 75%: additional $625,000 × 5% = $31,250. Total retainage: $125,000 + $31,250 = $156,250.

Answer Options
A
$156,250
B
$125,000
C
$250,000
D
$187,500

Why This Is the Correct Answer

At 50% completion: $1,250,000 × 10% = $125,000 retainage. From 50% to 75%: additional $625,000 × 5% = $31,250. Total retainage: $125,000 + $31,250 = $156,250.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.