EstatePass
Contract AdminContractseasy40% of exam part

A performance bond is typically written for what percentage of the contract amount?

Correct Answer

B) 100%

Performance bonds are typically written for 100% of the contract amount to ensure complete coverage for the owner in case the contractor defaults and the work must be completed by another contractor.

Answer Options
A
125%
B
100%
C
75%
D
50%

Why This Is the Correct Answer

Performance bonds are written for 100% of the contract amount because they must provide complete financial protection to the project owner. If a contractor defaults, the surety company needs sufficient funds to hire a replacement contractor to complete all remaining work. The bond amount must cover the full contract value to ensure the owner can finish the project without financial loss, as completion costs may equal or exceed the original contract amount.

Why the Other Options Are Wrong

Option C: 75%

50% coverage would be insufficient because if a contractor defaults midway through a project, the remaining work could cost significantly more than half the original contract amount due to mobilization costs, schedule delays, and premium pricing for emergency completion.

Option D: 50%

125% would be excessive for a standard performance bond, though some specialty projects may require higher coverage. Standard industry practice and most contract specifications call for 100% coverage as adequate protection.

Memory Technique

Think 'PERFECT Performance = 100%' - a performance bond must provide perfect (complete) coverage of the contract amount

Reference Hint

Look up 'Construction Bonds' or 'Surety Bonds' chapter in your Florida construction law reference materials, specifically the section on performance bond requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.