EstatePass
Contract AdminContractsmedium40% of exam part

A payment bond on a public project typically covers what percentage of the contract amount?

Correct Answer

A) 100%

Payment bonds on public projects are typically required to be 100% of the contract amount to ensure full coverage for labor and materials. This protects subcontractors and suppliers since they cannot file liens on public property.

Answer Options
A
100%
B
50%
C
125%
D
75%

Why This Is the Correct Answer

Payment bonds on public projects are required to be 100% of the contract amount under Florida law and federal regulations like the Miller Act. This full coverage ensures complete protection for subcontractors, suppliers, and laborers who cannot file mechanic's liens against public property. The 100% requirement guarantees that all legitimate claims for labor and materials can be satisfied through the bond.

Why the Other Options Are Wrong

Option B: 50%

50% coverage would be insufficient to protect all subcontractors and suppliers on a public project. This partial coverage could leave many legitimate claims unpaid, defeating the purpose of the payment bond as a substitute for lien rights on public property.

Option C: 125%

125% exceeds the standard requirement and would be unnecessarily costly. While performance bonds may sometimes exceed contract value, payment bonds are specifically tied to the actual contract amount to cover labor and material costs.

Option D: 75%

75% coverage would create a significant gap in protection, potentially leaving 25% of legitimate claims unpaid. This partial coverage would not adequately substitute for the lien rights that contractors lose on public projects.

Memory Technique

Remember 'Public = Perfect Protection = 100%' - public projects require complete payment bond coverage because no liens are allowed on government property.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.