A mixed-use development project includes 8,000 sq ft of retail space and 24 residential units. The impact fee is $2.50 per sq ft for retail and $1,200 per residential unit. What is the total impact fee?
Correct Answer
C) $48,800
The calculation is: (8,000 sq ft × $2.50) + (24 units × $1,200) = $20,000 + $28,800 = $48,800. Impact fees help fund infrastructure improvements needed to support new development.
Why This Is the Correct Answer
Option C correctly calculates the total impact fee by adding both components: retail space (8,000 sq ft × $2.50 = $20,000) plus residential units (24 units × $1,200 = $28,800). The sum equals $48,800. Impact fees are calculated separately for different land uses based on their specific rates and measurements, then combined for the total development cost.
Why the Other Options Are Wrong
Option A: $28,800
$28,800 represents only the residential portion of the impact fee calculation (24 units × $1,200). This answer fails to include the retail space impact fee of $20,000, resulting in an incomplete total that's $20,000 short of the correct amount.
Option B: $40,000
$40,000 appears to be an arbitrary figure that doesn't correspond to any logical calculation using the given rates. It's neither the retail portion ($20,000), residential portion ($28,800), nor their correct sum ($48,800).
Option D: $20,000
$20,000 represents only the retail space impact fee calculation (8,000 sq ft × $2.50). This answer omits the residential unit impact fee of $28,800, providing only half of the required total impact fee calculation.
Memory Technique
Remember 'MIX and MATCH': Mixed-use developments require calculating impact fees for each use type separately, then adding them together - Match each component to its rate, then MIX the totals.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
