EstatePass
Contract AdminProceduresmedium13% of exam part

A mechanical contractor installs ductwork 18 inches from its designed location due to a structural conflict. The original design showed the duct at elevation 12'-6" and it was installed at elevation 11'-0". What should be documented in the as-built drawings?

Correct Answer

B) The actual installed elevation of 11'-0"

As-built drawings should show the actual installed conditions, which is the 11'-0" elevation. The reason for the change should be documented separately in project records or RFIs.

Answer Options
A
The original elevation of 12'-6"
B
The actual installed elevation of 11'-0"
C
Both elevations with a note explaining the change
D
No documentation is needed since it's within acceptable tolerance

Why This Is the Correct Answer

As-built drawings are legal documents that must accurately reflect the actual installed conditions of the project. Their primary purpose is to show what was actually constructed, not what was originally designed. The actual elevation of 11'-0" is what exists in the field and what future maintenance, renovations, or inspections will encounter. While the reason for changes should be documented, it belongs in separate project records like RFIs, change orders, or project logs rather than cluttering the as-built drawings.

Why the Other Options Are Wrong

Option A: The original elevation of 12'-6"

Showing the original elevation of 12'-6" would be documenting the design intent rather than the actual installed condition, which defeats the purpose of as-built drawings that must reflect reality.

Option C: Both elevations with a note explaining the change

While documenting both elevations might seem thorough, as-built drawings should show only the actual installed conditions to avoid confusion and maintain clarity for future users of the drawings.

Option D: No documentation is needed since it's within acceptable tolerance

An 18-inch deviation from design is significant and must be documented regardless of tolerance, as it represents the actual field condition that differs from the original design.

Memory Technique

Think 'AS-BUILT = AS IT IS' - the drawings must show reality, not the original plan. The word 'built' refers to what actually got constructed.

Reference Hint

Florida Building Code Chapter 1, Administrative provisions regarding construction documents and as-built requirements, or project administration sections in contractor reference materials

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing