A masonry crew's productivity decreases from 100 blocks per hour to 75 blocks per hour due to cold weather conditions. If the original labor estimate was $12,000, what is the adjusted labor cost?
Correct Answer
A) $16,000
Productivity decreased by 25% (from 100 to 75 blocks/hour). This means 33% more time is needed (100/75 = 1.33). Adjusted cost = $12,000 × 1.33 = $16,000.
Why This Is the Correct Answer
When productivity decreases from 100 to 75 blocks per hour, the crew needs 33.33% more time to complete the same work. The time multiplier is 100÷75 = 1.333. Therefore, the adjusted labor cost is $12,000 × 1.333 = $16,000. This accounts for the additional time required due to reduced efficiency in cold weather conditions.
Why the Other Options Are Wrong
Option B: $14,400
$14,400 represents only a 20% increase ($12,000 × 1.20), which incorrectly assumes the productivity decrease of 25% translates to a 20% cost increase. This fails to account for the inverse relationship between productivity and time required.
Option C: $20,000
$20,000 represents a 67% increase, suggesting productivity dropped much more severely than the actual 25% decrease. This significantly overestimates the weather impact on labor costs.
Memory Technique
Remember 'Flip the Fraction': When productivity goes DOWN, costs go UP by the inverse ratio. 100÷75 = 1.33, so multiply original cost by 1.33.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?