EstatePass
Business & FinanceAccountingmedium32% of exam part

A job has a contract value of $500,000 with costs to date of $300,000 and estimated costs to complete of $150,000. Using the percentage-of-completion method, what percentage of the job is complete?

Correct Answer

B) 67%

Percentage complete = Costs to date ÷ Total estimated costs. Total estimated costs = $300,000 + $150,000 = $450,000. $300,000 ÷ $450,000 = 66.7% or approximately 67%.

Answer Options
A
60%
B
67%
C
75%
D
80%

Why This Is the Correct Answer

The percentage-of-completion method calculates project completion based on costs incurred versus total estimated costs, not contract value. The formula is: Costs to date ÷ Total estimated costs. Total estimated costs equals costs to date ($300,000) plus estimated costs to complete ($150,000) = $450,000. Therefore, $300,000 ÷ $450,000 = 0.667 or 67%.

Why the Other Options Are Wrong

Option A: 60%

60% incorrectly uses the contract value in the calculation ($300,000 ÷ $500,000 = 60%), but percentage-of-completion is based on costs, not contract value.

Option C: 75%

75% appears to use an incorrect total cost figure, possibly excluding some costs or using the wrong denominator in the calculation.

Option D: 80%

80% significantly overstates the completion percentage and doesn't align with any logical calculation using the given figures.

Memory Technique

Remember 'CTC' - Costs To Complete: Add costs to date + costs to complete for your denominator, then divide costs to date by that total.

Reference Hint

Look up 'Percentage-of-Completion Method' or 'Project Accounting' in construction management or accounting sections of your reference materials.

More Business & Finance Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing