EstatePass
Contract AdminContractshard40% of exam part

A general contractor's subcontractor abandons the job with $45,000 of work remaining. The general contractor hires a replacement subcontractor who charges $52,000 for the same work. What damages can the general contractor typically claim?

Correct Answer

A) $7,000

The general contractor can typically claim the difference between the original subcontract price and the cost to complete the work with a replacement contractor: $52,000 - $45,000 = $7,000 in additional costs caused by the breach.

Answer Options
A
$7,000
B
$52,000
C
$45,000
D
$97,000

Why This Is the Correct Answer

When a subcontractor breaches a contract by abandoning work, the general contractor is entitled to damages that put them in the same financial position they would have been in if the breach hadn't occurred. This follows the fundamental principle of contract damages - compensation for the actual financial harm caused by the breach. The general contractor originally expected to pay $45,000 for the work, but due to the abandonment, they had to pay $52,000 to complete it. The $7,000 difference represents the direct financial harm caused by the subcontractor's breach.

Why the Other Options Are Wrong

Option C: $45,000

This represents the value of work remaining under the original contract, not the damages. The general contractor would have paid this amount anyway if the original subcontractor had completed the work as agreed.

Option D: $97,000

This incorrectly adds the original remaining work value ($45,000) plus the replacement cost ($52,000), which would be double-counting. This doesn't represent any recognized measure of contract damages.

Memory Technique

Think 'DELTA DAMAGES' - you only get the difference (delta) between what you expected to pay and what you actually had to pay due to the breach.

Reference Hint

Florida Building Contractors Reference Manual - Contract Law chapter, specifically the section on breach of contract remedies and damages

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.