EstatePass
Contract AdminPreconstructionmedium27% of exam part

A general contractor receives three subcontractor bids for electrical work: $125,000, $142,000, and $98,000. What should be the contractor's primary concern regarding the lowest bid?

Correct Answer

A) The bid may contain errors or omissions

When a bid is significantly lower than others (in this case, $98,000 vs. $125,000 and $142,000), the primary concern should be potential errors or omissions in the estimate. A bid that's substantially lower may indicate the subcontractor missed scope items or made calculation errors.

Answer Options
A
The bid may contain errors or omissions
B
The electrical contractor lacks proper licensing
C
The materials specified are of inferior quality
D
The project schedule will be extended

Why This Is the Correct Answer

When one bid is significantly lower than others (in this case $98,000 compared to $125,000 and $142,000), the primary concern should be potential errors or omissions in the estimate. A 22-28% difference from the other bids is a red flag that suggests the subcontractor may have missed scope items, made calculation errors, or failed to include all required work. This could lead to change orders and cost overruns during construction. The general contractor has a duty to investigate unusually low bids before acceptance.

Why the Other Options Are Wrong

Option B: The electrical contractor lacks proper licensing

While licensing is important, this should be verified for all bidders regardless of bid amount. The question specifically asks about the concern regarding the lowest bid amount, not general contractor qualification issues. Licensing verification is a standard pre-qualification step that occurs before bid evaluation.

Option C: The materials specified are of inferior quality

Material quality concerns are not necessarily indicated by a low bid amount alone. The specifications should clearly define material requirements, and all bidders should be pricing to the same specifications. Material quality issues would require specification review rather than bid amount analysis.

Option D: The project schedule will be extended

A lower bid amount does not inherently indicate schedule extension issues. In fact, a lower bid might suggest faster completion if the contractor has better efficiency or lower overhead. Schedule concerns should be evaluated separately from bid pricing through schedule submittals and contractor capacity analysis.

More Contract Admin Questions

People Also Study

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing